For Free Headlines Submit Your Email
Friday, April 26, 2024 2:38 GMT
Genel Energy has announced an update on activity at the Taq Taq Oil Field (Genel 44% working interest), as testing of the TT-34 well is nearing completion. The well has produced from all zones tested, at a maximum combined flow rate of over 3,900 bopd with 28/64″ choke. With the inclusion of test production, gross production from the Taq Taq field is currently c.13,650 bopd.Individual zone testing is now underway, which will determine the long-term production strategy. Genel expects the well to be placed on production around the middle of January with an initial flow rate of 1,500-2,000 bopd. The rig has moved to drill the TT-35 well, also on the northern flank of the field, which is now preparing to spud.